CIVIL ENGINEERING AND ELECTRICAL WORK CONTINUES - Weeks of September 29 and October 6, 2008

Laying and compacting of stone continued for the access road and crane pad. The small transformer providing service to the tennis court lights will remain in service pending the resolution of the placment of electrical components and transmission lines. The electrical configuration will be discussed by the town the week of Oct 13. Most of the WTG compnents for the nacelle have been received at AAER in Canada. There may be a delay in shipment of the tower from Korea that may delay WTG eraction until the end of December 2008.

Some new pictures are below.


. Looking NW from Education Lane

Close-up access through trees (looking NW) .

. Staging pad (Looking NW)

Access Road (looking E) .

. Crane Pad (looking E from WTG Foundation) (Looking W)

Crane pad (Looking E)