CIVIL ENGINEERING AND ELECTRICAL WORK CONTINUES - Weeks of September 29 and October 6, 2008
Laying and compacting of stone continued for the access road and crane pad.
The small transformer providing service to the tennis court lights will remain in service pending the
resolution of the placment of electrical components and transmission lines. The electrical configuration
will be discussed by the town the week of Oct 13. Most of the WTG compnents for the nacelle have been received
at AAER in Canada. There may be a delay in shipment of the tower from Korea that may delay WTG eraction until the end