SITE PREPARATION WORK CONTINUES - Week of August 25, 2008

This week a lot of essential (albeit non-exciting) earth moving work was being done to backfill trenches and continue preparations for laying the crushed stone access road and turbine assembly areas. Behind-the-scenes work was in full force with the electrical contractors working on electrical equipment final design and procurement and liaison with National Grid on electrical interconnect plans. A few new trenches were dug for grouding wires.

Sorry, no new pictures this week -- The site looks pretty much the same as it did last week.